Srinakarin Campus Development

 

In celebrating St. Mark’s 20th anniversary, the time has arrived for St. Mark's to take another significant step forward in securing the future for our young.  The management of St. Mark’s is pleased to officially inform you of our development on our second campus on Srinakarin Road, where construction is expected to be completed in 2022.  

Once completed, our new campus will house both the primary and secondary sections, with state-of-the-art facilities.  Join us and grow with us.

 

DEVELOPMENTAL TIMELINE FOR SRINAKARIN CAMPUS

17 October 2020

Ground Breaking Ceremony

25 December 2020

 

Approval of Curriculum and School Name

by the Office of the Private Education Commission (OPEC)

Ministry of Education

27 January 2021

Approval of Construction Permit

by Bangkok Metropolitan Administration (BMA)

1 February 2021

Construction Commence 

Demolition of Existing Building

7 February 2021

Start of Bore Pile Construction

Foundation for Indoor Gymnasium

19 February 2021 Demolition of Old Building Completed

21 April

2021

Complete Construction of Concrete Floor for School Gymnasium

21 May

2021

Construction of steel frames, including steel columns and roof truss structure for School Gymnasium

28 May

2021

Construction Contract Awarding Ceremony for Main School Building, Srinakarin Campus

17 June

2021

 Installation of the 800 square-metre prefabricated roof

July 21

2021


Foundation Work on Main School Building

August 31

2021

Piling Work for the School Main Building

September 17

2021

Piling Work Completed for the School Main Building

November 12

2021

Construction of retaining wall, Excavation of soil to make car parking basement

December 05

2021

Soil excavation and construction of footing for car park basement

January 26

2022

Construction of the building's underground car park floor

February 28

2022

Construction of the building’s ground floor using post-tension

March 23

2022

Construction of the building’s first 3 floors

April 20

2022

Construction of columns and shear walls of level 2 leading to level 3

August 11

2022

Construction completed for all 8 - story structural work for our school building

September 16

2022

Bricking and plastering of classroom walls have progressed to 70%